Running 10 MW for 4,818 h/yr gives 884 t of hydrogen annually. The levelized cost is 4.52 €/kg (largest component: Electricity), lower than your sale price of 6 €/kg, so you keep a margin.
Hydrogen production
884t/yr
2,422 kg/day on average · 183 kg/h at full load
Levelized cost (LCOH)
4.52€/kg
136 €/MWh (LHV)
Electricity used
48.2GWh/yr
54.5 kWh/kg with degradation counted
Efficiency
61.2%
LHV · 72.3% HHV
Water consumption
13,262m³/yr
15 L/kg (stoichiometric 8.9)
Oxygen by-product
7,020t/yr
Stack replacements
1
every 16.6 years (80,000 h)
Total capex
€16,000,000
1,600 €/kW
Project NPV at your sale price
€15,247,042
6 €/kg, 7% WACC
CO₂ avoided vs grey H₂
8,841t/yr
≈10 kg CO₂ per kg from SMR without capture
Equivalent uses
7,368 FCEVs
equal to 5,013 t of ammonia · 2,959 m³ of diesel
Electrolyzer types (typical 2023–2025 figures)
| Technology | System kWh/kg | Efficiency (LHV) | Stack life (h) | Installed capex (€/kW) | Notes |
|---|---|---|---|---|---|
| Alkaline (AEL) | 50–55 | 61–67% | 60,000–90,000 | 1,400–2,000 | proven and cheapest, ramps up more slowly |
| PEM | 52–58 | 57–64% | 50,000–80,000 | 1,700–2,500 | small footprint, quick response, needs iridium/platinum |
| SOEC | 37–42 + heat | 75–85% | 20,000–40,000 | 2,500–4,000+ | runs hot, works best with waste heat or steam |
| AEM | 50–57 | 58–66% | <30,000 | early market | no PGMs, small units |
- Total up O&M, electricity, water, heat, capex × CRF and PV of stack replacements × CRF, then divide by the kg produced per year to get LCOH. The calculation leaves out taxes, grid fees, storage, transport and subsidies.
- A real plant seldom holds one flat capacity factor. Variable renewables bring minimum-load limits and ramp rates that trim output; buffer storage or a top-up from the grid lifts utilisation again.
- Capex figures span a wide band and shift fast. Alkaline systems from China are quoted far below installed costs in the West. For current numbers, see the latest IEA Global Hydrogen Review.