From electrons to LCOH
Water is split into hydrogen and oxygen by an electrolyzer powered with renewable electricity. Physics sets a fixed minimum of 39.4 kWh per kg. Cost is another matter, and it depends on electrolyzer efficiency and price, annual operating hours and the electricity tariff. The calculator treats them together in four steps:
- Output. Electrolyzer power × operating hours (set by the capacity factor of your supply) ÷ specific energy use gives kg per year. Stack degradation raises consumption over a stack’s life, so the tool uses the lifetime average.
- Inputs and by-products. Water, oxygen output and, with SOEC, steam.
- Cost per kg (LCOH). Capex is spread across the years by the capital recovery factor at your WACC, and stack replacements get the same treatment after discounting to the present. Then come fixed O&M, electricity, compression, water and heat, and the total is divided by yearly output.
- Sensitivity. LCOH is plotted against capacity factor for three power prices, which shows the cheap-but-intermittent versus expensive-but-firm trade-off better than a table.
Equations
Case study: 10 MW alkaline, wind–solar PPA
Default setup: a 10 MW alkaline electrolyzer (52 kWh/kg new) on a hybrid solar and wind supply, 55% capacity factor, €45/MWh.
- Roughly 4,820 full-load hours a year and 48 GWh of electricity.
- Degradation of 0.12%/1,000 h lifts lifetime-average use to about 54.5 kWh/kg (61% LHV efficiency). The plant makes about 880 tonnes of hydrogen yearly, i.e. 2.4 t daily.
- Water need is about 13,000 m³, with 7,000 t of oxygen released.
- Capex at €1,600/kW totals €16 million; one stack is replaced after about 16–17 years.
- LCOH ≈ €4.5/kg: electricity €2.45, capital €1.55, O&M €0.36, stack replacement €0.12 and water €0.03 per kg.
Priced at €6/kg, the hydrogen gives an NPV near +€15 million. With the 1 MW PEM on solar preset, LCOH tops €10/kg because the plant is small, capex is higher and capacity factor is only 22%. The 2030 target preset (€700/kW, €25/MWh) illustrates the roughly €2/kg that policymakers have in view.
Reading the results
- Production is given in tonnes per year, as a daily mean, and as hourly output at full load.
- LCOH should be weighed against grey hydrogen (about 1–3 per kg), subsidy auction prices, or whatever fuel is being displaced; the per-MWh LHV figure lines it up with natural gas.
- Cost breakdown: when electricity dominates, work on efficiency and power price; when capital does, raise utilisation.
- Sensitivity chart: each curve drops sharply at low capacity factors, then flattens past 50–60%. The best spot trades cheaper intermittent power against idle capital.
Technology comparison
| Electrolyzer type | Energy per kg, system level | LHV efficiency | Stack lifetime | Installed capex, 2023–24 |
|---|---|---|---|---|
| Alkaline (AEL) | 50–55 kWh/kg | 61–67% | 60,000–90,000 h | 1,400–2,000 per kW |
| PEM | 52–58 kWh/kg | 57–64% | 50,000–80,000 h | 1,700–2,500 per kW |
| SOEC | 37–42 kWh/kg + heat | ~75–85% incl. heat | 20,000–40,000 h | 2,500–4,000+ per kW |
| Anion exchange membrane, AEM | 50–57 kWh/kg | 58–66% | < 30,000 h | early market |
Rules of thumb: 1 kg H₂ = 33.3 kWh (LHV) = 39.4 kWh (HHV) ≈ 11.1 Nm³. Fuel-cell cars use about 0.8–1 kg per 100 km; one tonne of hydrogen makes about 5.7 t of ammonia.
Ways to cut LCOH
- Use the plant more. Mixing wind and solar, or topping up from the grid, can lower LCOH even if average power costs more.
- Build renewables larger than the electrolyzer, so the latter spends more hours at full load.
- Sell by-products. Selling oxygen or recovered low-temperature heat can lower cost by a few percent.
- Watch stack lifetime and degradation, since a longer-lived stack may skip an expensive replacement.
- Count compression and storage. Hydrogen delivered at 350–700 bar, or as a liquid, needs another 2–12 kWh/kg (set in the compression field) and storage on top.
- Supply side: the wind farm calculator and the solar panel calculator model the power source.
Model limits
The model holds capacity factor and power price constant. Real renewable supply fluctuates, and limits on minimum load, ramping, storage and offtake reduce effective utilisation. Not modelled: taxes, grid fees, land, financing structure, transport and subsidies. Capex changes fast and differs by supplier and region, so consult recent sources like the IEA Global Hydrogen Review before trusting one figure.
Method & assumptions
Yearly production in kg = MW × 8,760 × CF × 1,000 ÷ specific energy use (kWh/kg). Stack degradation (%/1,000 h) makes that specific use rise until each replacement resets it, so what is applied is the mean across a stack's life. For efficiency on an LHV basis, use 33.33 ÷ kWh/kg; water is kg × L/kg; oxygen is about 7.94 kg per kg H₂. To get LCOH, add annualised capex (CRF at your WACC), the annualised present value of stack replacements, fixed O&M, electricity, compression and water (and steam for SOEC), then divide by annual kg.
Frequently asked questions
Power demand for one kg of hydrogen?
Water consumption of hydrogen production?
Green hydrogen price per kg?
Output of a 1 MW electrolyzer?
What does LCOH mean?
PEM or alkaline: which wins?
Why is capacity factor such a big lever?
Sources & references
- IEA — Global Hydrogen Review 2024
- IRENA (2020). Green Hydrogen Cost Reduction: Scaling up Electrolysers to Meet the 1.5 °C Climate Goal
- Clean Hydrogen Partnership — Strategic Research and Innovation Agenda (electrolyser KPIs)
- US DOE Hydrogen and Fuel Cell Technologies Office — Hydrogen production via electrolysis