LCOE is about 45.4 €/MWh, well under the 70 €/MWh market price (a margin of 24.6 €/MWh). The biggest cost item is Capital.
LCOE
45.4€/MWh
4.54 €-cents/kWh
Capital recovery
37.4€/MWh
82% of LCOE
Fixed O&M
8€/MWh
Fuel + variable O&M
0€/MWh
Carbon cost
0€/MWh
0 kg CO₂/MWh
Annual output per kW
1,577kWh/kW
1,577 full-load hours
Capital recovery factor
7.26%/yr
6% over 30 years
Interest during construction
3%
1-year build
Margin vs market
24.6€/MWh
Technology comparison using typical inputs
| Technology | Capex /kW | CF | Life | WACC | LCOE /MWh | kg CO₂/MWh |
|---|---|---|---|---|---|---|
| Solar PV, utility scale (your inputs) | 750 | 18% | 30 | 6% | 45.4 | 0 |
| Residential rooftop solar PV | 1,400 | 14% | 25 | 5% | 102 | 0 |
| Onshore wind | 1,200 | 36% | 25 | 6% | 41.9 | 0 |
| Offshore wind | 2,800 | 45% | 25 | 7% | 87.5 | 0 |
| Combined-cycle gas plant (CCGT) | 1,000 | 55% | 30 | 7% | 78 | 370 |
| Gas peaker (open cycle) | 750 | 10% | 30 | 7% | 172.6 | 561 |
| Coal (supercritical) | 2,200 | 60% | 40 | 7% | 80.2 | 851 |
| Nuclear (new large LWR) | 7,000 | 90% | 60 | 7% | 106.6 | 0 |
| Hydropower (large) | 2,800 | 45% | 60 | 6% | 63.7 | 0 |
| Geothermal (flash) | 4,000 | 80% | 30 | 7% | 71.9 | 0 |
| Biomass (dedicated) | 2,500 | 75% | 25 | 7% | 113.4 | 0 |
- The preset costs are typical worldwide values for 2023–2024 in USD-like money (IRENA, Lazard, IEA/NEA). Real projects differ a lot by country, site and contract, so adjust the inputs to fit your case.
- LCOE is measured in real terms, before tax, at the plant gate. It leaves out system costs (backup, storage, grid), differences in market value and subsidies, so be careful when comparing dispatchable with variable technologies.