Bio, geo & hydrogen calculator

Biogas plant calculator: from feedstock mix to methane, electric kW, heat and digestate

Start from the daily digester feed, be it food waste, beet, silage, manure or slurry, to get gas and methane volumes, CHP electric and thermal output or biomethane, digester size, loading rate and a financial view.

Editable share link Branded PDF report Free · no sign-up

Results

The 3,150 m³ of biogas produced daily (53% methane) would fuel a CHP engine of roughly 299 kWe running 8,000 h a year, which yields 2.39 GWh of electricity and 2.57 GWh of heat. Feeding the digester at 2.4 kg VS/m³·d is a sound choice; most plants operate between 1.5 and 4. Payback is about 13.2 years, yet the IRR (2.7%) falls short of your 6% discount rate. Higher tariffs, heat sales or cheaper feedstock would be needed.
CHP electrical capacity
299kWe
2,201,456 kWh/yr exported
Thermal output
322kWth
1,929 MWh a year left over once the digester heat is covered
Biogas production
3,150m³/day
1,150 thousand m³/yr
Methane content
52.7%
1,661 m³ CH₄/day
Primary energy (methane)
5.98GWh/yr
683 kW continuous
Digester volume
2,520m³
60 days retention · OLR 2.45 kg VS/m³·d
Digestate
13,821t/yr
37.9 t a day, with 10% of the mass turned into gas
Annual revenue
€361,087
crop cost 175,200 €/yr
Payback
13 yr 3 mo
capex 1,345,999 €
IRR
2.7%
Biogas by feedstock
Destination of the methane energy

Feedstock mix

Feedstockt/dayShare of massDM %Biogas m³/tCH₄ %Biogas m³/dayShare of gas
Cattle slurry3071%10255575024%
Maize silage1229%33200522,40076%

Typical values by feedstock (per tonne of fresh matter)

FeedstockDry matter %Volatile solids % of DMBiogas m³/tMethane %Biogas m³/t VS
Cattle slurry10802555313
Pig slurry6802265458
Cattle manure (solid)25806055300
Poultry litter / dung40758060267
Maize silage339520052638
Grass silage359018054571
Sugar beet239013052628
Food waste (source-separated)259014060622
  • The yields are mid-range figures from the literature (FNR/KTBL). Actual yields swing by ±20–30% depending on silage quality, how diluted the slurry is, storage losses and retention time. Before investing, run laboratory BMP tests on your own feedstock.
  • Methane energy is based on an LHV of 9.97 kWh/Nm³. Digestate is roughly the mass that went in less the mass of gas that left, and it retains nearly all the nitrogen, phosphorus and potassium from the feedstock.
  • In many countries energy crops are capped (for example by limits on the share of maize), or tariffs are paid only for waste or manure, so check the rules where you are.

Feed decides output

Bacteria in a warm, airtight tank break organic matter down into methane and carbon dioxide, and how much gas appears depends mainly on what goes in. A tonne of slurry is mostly water. A tonne of silage or food waste is dense with energy. Pick a feedstock mix from eight common materials and the tool traces the energy through every stage:

  1. Gas volumes: biogas and methane for each material, using mid-range literature yields and usual methane shares (FNR/KTBL).
  2. Energy content: the primary energy left in the methane once a small slip loss is taken off.
  3. Conversion route: either a CHP gas engine (electricity, heat, the plant’s own power and digester heating) or biomethane upgrading for grid injection.
  4. Tank: a digester volume set by retention time, and the organic loading rate that follows.
  5. By-products and money: digestate and economics, covering crop purchases and the gate fees food waste can earn.

Equations

Biogas (m³/day) = Σ tonnes_i × yield_i (m³/t fresh matter) Methane = Σ biogas_i × CH₄ share_i Primary energy (kWh) = CH₄ (m³) × 9.97 × (1 − slip) CHP: electricity = primary × η_el heat = primary × η_th Engine size (kWe) = annual electricity / full-load hours Digester volume (m³) = daily fresh mass (≈ t) × HRT (days) OLR (kg VS/m³·d) = Σ tonnes_i × DM_i × VS_i × 1,000 / volume Digestate = input mass − mass of CH₄ and CO₂ released

Example: dairy slurry with maize silage

The default plant digests 30 t/day of cattle slurry (from roughly 500–600 dairy cows) and 12 t/day of maize silage.

  • Gas per day: 750 m³ from the slurry, 2,400 m³ from the maize. The silage makes up 29% of the mass yet 76% of the gas.
  • The mix totals 3,150 m³/day at roughly 53% methane. That is 1,660 m³ of methane, or 6.0 GWh a year of energy (683 kW running continuously).
  • A CHP engine (40% electrical, 43% thermal, 8,000 h/yr) is sized near 300 kWe. Output is 2.4 GWh of electricity, of which 2.2 GWh is exported after 8% own use, plus 2.6 GWh of heat.
  • At 60 days of retention the digester volume is about 2,500 m³, and an organic loading rate of 2.45 kg VS/m³·d sits well inside the stable band.
  • Each year about 13,800 t of digestate returns to the fields.

Revenue is about €360,000 a year: electricity sold at €0.15/kWh, plus 40% of the surplus heat at €0.04/kWh. The 4,380 t of maize costs €175,000 at €40/t. With capital at €4,500/kWe, payback takes about 13 years and the IRR stays under 3%. For this reason farm biogas relies on tariffs, heat customers or low-cost waste feedstocks.

What the outputs mean

  • CHP capacity / biomethane output states how big the plant is.
  • Methane content below 50% points to a mix short of fats and proteins, or to a process problem.
  • Organic loading rate: acidification and foaming risk rises above about 4–4.5 kg VS/m³·d, while a value under 1 means the digester is bigger than it needs to be.
  • Energy flow chart traces how much methane energy ends up as saleable electricity and heat. Heat that goes unused is the biggest economic lever.
  • Feedstock table sets each material’s share of mass against its share of gas.

Feedstock reference

  • Cattle slurry: 8–11% dry matter, 20–30 m³ biogas per fresh tonne, 55–60% methane.
  • Pig slurry: 4–7% DM, 20–35 m³/t, 60–65% methane.
  • Solid cattle manure: 20–25% DM, 40–80 m³/t, 55% methane.
  • Poultry dung: 30–50% DM, 70–90 m³/t, 60% methane.
  • Maize silage: 30–35% DM, 170–230 m³/t, 52% methane.
  • Grass silage: 25–40% DM, 170–200 m³/t, 54% methane.
  • Sugar beet: 20–25% DM, 120–140 m³/t, 52% methane.
  • Food waste: 15–30% DM, 100–200 m³/t, 58–62% methane.

Improving yield and returns

  • Find a use for the heat. Drying, greenhouses or district heating can add 20–30% to revenue.
  • Co-digest wastes. Food waste and crop residues raise gas yield and can earn a gate fee instead of costing money.
  • Keep slurry undiluted. Rainwater and wash water cut yield per tonne and take up digester volume.
  • Seal the digestate store. A gas-tight cover captures leftover gas (often 5–10% more) and curbs methane emissions.
  • Feed in small, frequent portions, which keeps the microbes healthy and the methane share high.

Uncertainty

All yields are mid-points from the literature. Silage quality, storage losses, slurry dilution and retention time can swing real values by ±20–30%, so run laboratory biomethane-potential (BMP) tests before you invest. A continuously stirred mesophilic digester, even feeding all year and fresh matter of about 1 t/m³ are assumed. Digester heat demand through the seasons, hydrogen-sulphide treatment, digestate processing and permits lie outside the model, and subsidies and energy-crop limits vary by country.

Method & assumptions

Total biogas is Σ (tonnes per day × typical yield per tonne of fresh matter); methane is Σ biogas × CH₄ share. Primary energy = CH₄ × 9.97 kWh/Nm³ × (1 − slip). In a CHP unit, electricity = primary × ηel and heat = primary × ηth, and the engine is sized as annual electricity ÷ full-load hours; parasitic load and digester heating come off the output. A biomethane route counts the upgraded CH₄ volume minus the electricity the upgrading consumes. Digester volume = daily fresh mass (≈ 1 t/m³) × retention time, with the organic loading rate given as kg volatile solids per m³ per day. Digestate = mass in minus the CH₄ and CO₂ mass leaving as gas.

Frequently asked questions

What biogas yield can I expect per tonne of manure?
The more solid the material, the more gas a tonne gives. Cattle slurry sits at 20–30 m³, pig slurry at 20–35 m³, solid cattle manure at 40–80 m³ and poultry dung at 70–90 m³ (all biogas, per tonne fresh). Crops beat all of them, with maize silage near 200 m³ and grass silage at 170–200 m³.
What electricity can 1 m³ of biogas provide?
Methane holds about 10 kWh/m³, so gas that is 55% methane contains about 5.5 kWh per m³. Put it through a CHP gas engine with 38–42% electrical efficiency and each m³ yields roughly 2.0–2.3 kWh of electricity, alongside 2.3–2.5 kWh of heat you can use.
How big a herd does a biogas plant need?
A single dairy cow produces 50–60 kg of slurry daily. That converts to around 1.3–1.5 m³ of biogas and about 0.12 kW of electrical output running non-stop. To feed a 50–100 kW CHP on slurry alone you would need several hundred animals, which is why farm plants usually top up with energy crops or food waste.
What share of biogas is methane?
The usual range is 50–65%. The balance is mainly carbon dioxide, with hydrogen sulphide, water vapour and ammonia in trace amounts. Fat and protein feeds push methane higher; a carbohydrate crop such as maize lands near 52%.
Hydraulic retention time and organic loading rate: what do they mean?
Dividing digester volume by daily input gives retention time, the mean number of days feed spends inside. Slurry plants run 20–30 days and energy-crop plants 60–100 days. Organic loading rate is the other yardstick: volatile solids (kg) fed per m³ of tank each day. For stirred tanks the normal band is 1.5–4 kg VS/m³·d.
Digestate: what is it and how much is produced?
What leaves the tank after digestion is a nutrient-rich fertiliser that still contains practically all the nitrogen, phosphorus and potassium that went in. Subtract the released gas from the input mass and you have its weight, typically 85–95% of the input for manure-based plants.
Should biogas go to electricity or to biomethane?
Simplicity favours a CHP engine, particularly on farms with a heat customer nearby. Biomethane means stripping out CO₂ to reach about 97–99% methane, after which the gas can enter the grid and go wherever it is worth most: heating, industry or transport. Paying for the upgrade only makes sense at scale, usually above about 250–500 m³/h of raw biogas.

Sources & references

  1. FNR (Fachagentur Nachwachsende Rohstoffe): Guide to Biogas: From Production to Use, 5th ed., 2010
  2. IEA Bioenergy Task 37: Energy from Biogas
  3. IEA (2020). Outlook for biogas and biomethane: Prospects for organic growth
  4. KTBL: Gasausbeute in landwirtschaftlichen Biogasanlagen (biogas yields of agricultural feedstocks)