Most Malaysians meet the power sector once a month, as a bill from TNB, SESB or SEB. Four things sit behind it: three separate grids, a large fleet of privately owned stations, one central buyer and a regulator, with a tariff formula that was rebuilt in 2025. This page explains who does what, what fuels the system and how your invoice total is calculated.
| Looking for | Page |
|---|---|
| Current tariffs and data | Malaysian electricity page and TNB tariff page |
| Country overview | Malaysia’s country page |
Who serves which region
There is no national grid. Sabah and Sarawak lie across the sea on Borneo, so each runs a system of its own.
| Area | Operator | Who owns it | Fuel base |
|---|---|---|---|
| Peninsular Malaysia | Tenaga Nasional Berhad (TNB) | Stock-exchange listed, with government-linked shareholders such as Khazanah | Mainly coal and gas; hydro, and more and more solar |
| Sabah and Labuan | Sabah Electricity Sdn Bhd (SESB) | A TNB subsidiary; transfer to the Sabah state is planned | Chiefly gas, with some hydro and diesel |
| Sarawak | Sarawak Energy Berhad (SEB) | Owned by the Sarawak state government | Hydropower first, then gas and coal |
| Peninsula in figures | Value |
|---|---|
| Installed capacity | 27,333 MW |
| Record peak demand | 21,049 MW on 28 May 2025 |
| Power trading partners | Thailand (north), Singapore (south) |
That makes the peninsula far larger than the other two systems. Sarawak, for its part, sells hydropower across the border to West Kalimantan in Indonesia.
Who does what on the peninsula
Competition between sellers does not exist here; one buyer organises everything. Roles are split as follows.
| Player | Role |
|---|---|
| Suruhanjaya Tenaga (Energy Commission) | Peninsular regulator. Issues generation licences and, under the Electricity Supply Act 1990, proposes tariffs for government approval. Sabah has had its own regulator since January 2024, the Energy Commission of Sabah (ECoS); Sarawak relies on state law. |
| Generators | TNB’s own plants plus independent power producers (IPPs). Malaysia licensed its first IPPs in the early 1990s, after the blackouts of 1992, to firms such as YTL Power and Genting Sanyen. IPPs now hold over half of peninsular capacity, mostly under long-term power purchase agreements that pay for both capacity and energy. |
| The Single Buyer | A ring-fenced department of TNB since 2012. Plans and schedules at least cost, buys from every generator and passes the costs to the grid business. |
| Grid System Operator (GSO) | Keeps the high-voltage grid balanced in real time at 50 Hz. See grid frequency and balancing. |
| TNB Grid and TNB Distribution | Operate the 500 kV, 275 kV and 132 kV transmission lines and the distribution networks, and handle customers. |
New plants are chosen through Energy Commission tenders, such as the Large Scale Solar (LSS) rounds and the calls for gas capacity. Renewable power can also be sold across borders through Energy Exchange Malaysia (ENEGEM), operating since 2023.
The fuel mix
The table below rounds Ember and Energy Commission numbers for 2023–2024.
| Fuel | Share | Key stations |
|---|---|---|
| Coal | ~45% | Manjung (Janamanjung, about 4.1 GW), Tanjung Bin, Jimah, Kapar |
| Natural gas | ~34% | Combined-cycle stations at Pasir Gudang, Prai, Kapar and Track 4A; SESB’s Sabah plants |
| Hydropower | ~17–18% | Bakun 2,400 MW, Murum 944 MW and Batang Ai in Sarawak; Pergau 600 MW and Kenyir (Sultan Mahmud) 400 MW in the peninsula |
| Solar | ~2% (plus rooftop self-consumption) | LSS solar farms; rooftop systems under NEM and Solar ATAP |
| Other | ~1% | Biomass, biogas, diesel |
Coal is nearly all imported, mostly from Indonesia and Australia. Gas comes from offshore fields near Peninsular Malaysia, Sabah and Sarawak, supplemented by imported LNG landed at the Melaka and Pengerang regasification terminals. Because Sarawak runs mainly on hydro, it has among the cleanest grids in Southeast Asia and low industrial power prices, which draw aluminium smelters and data centres.
Each large station appears on the power plants map.
How your tariff is determined
TNB’s income has been governed by Incentive-Based Regulation (IBR) since 2014. For every regulatory period the Energy Commission sets a revenue allowance that covers operating costs, depreciation and a return on assets, and a utility that meets reliability targets earns an incentive on top. Fuel and generation are not part of that allowance and are passed through separately.
For Peninsular Malaysia, Regulatory Period 4 (RP4, 2025–2027) approved a base tariff averaging 45.40 sen/kWh. Households received a new bill layout in July 2025:
| Charge | Covers |
|---|---|
| Energy charge | Fuel and generation; the rate is lower up to 1,500 kWh a month and higher beyond |
| Capacity charge | Keeping power stations ready to run |
| Network charge | Transmission and distribution |
| Retail charge | Billing and customer service; fixed, and waived for small users |
| Automatic Fuel Adjustment (AFA) | A monthly surcharge or rebate when fuel costs move |
| Energy efficiency incentive | A rebate for modest monthly consumption |
The Automatic Fuel Adjustment moves monthly, whereas its predecessor, the Imbalance Cost Pass-Through (ICPT), was reviewed only twice a year. Changes inside ±3 sen/kWh are decided by the Energy Commission; anything beyond needs the government to agree. Over 2026 the AFA swung from a 4.99 sen/kWh rebate in January to a 3.60 sen/kWh surcharge in November.
| Other bill items | Rule |
|---|---|
| Service tax | 8% on household use above 600 kWh a month |
| Renewable energy fund levy (KWTBB) | 1.6%, once consumption exceeds 300 kWh |
Treat these numbers as a rough sketch only.
| To do this | Use |
|---|---|
| See live rates | TNB tariff page |
| Run your own case | electricity bill calculator |
| Walk through a real invoice | how to read your electricity bill |
Compared internationally, Malaysian tariffs are cheap, because fuel costs have been suppressed for years. Gas sold to the power sector has had a regulated price under the market level, and at times the Kumpulan Wang Industri Elektrik fund has covered fuel price increases for the government. Why that matters is covered in fossil fuel subsidies explained.
Rooftop solar and other clean options
A customer who wants greener electricity can pick from three schemes.
- Solar ATAP replaced net energy metering (closed mid-2025) on 1 January 2026. Panels on your roof cover your own load, and surplus exports earn credits valued at the energy charge rate for homes and at the average system marginal price for businesses. A credit has to be used in the billing month it was earned, and participation can run up to 10 years. Read more on Malaysian solar.
- Green Electricity Tariff (GET) works by paying TNB an extra per-kWh amount, with which it buys renewable energy certificates to match your use.
- Corporate Renewable Energy Supply Scheme (CRESS) opened in September 2024; the Single Buyer began accepting applications on 30 September 2024. The company agrees a contract with a renewable developer and TNB’s grid carries the power, for a system access charge. Never before had Malaysia let third parties onto its grid.
LSS tenders procure the utility-scale solar plants. LSS5 (2024) offered 2,000 MW, and LSS6 covers about 2.5 GW of solar with batteries.
What is changing
Under the National Energy Transition Roadmap, renewables should reach 70% of capacity by 2050 and no new coal will be built. Expect these consequences:
- Solar and batteries added to the peninsular grid, with stronger networks to carry them.
- Gas plants built to take over as coal retires.
- Stronger ties to Thailand, Singapore and Sarawak by cable, so Malaysia counts for more in the ASEAN Power Grid (energy in Southeast Asia gives the wider picture).
- Data-centre clusters in Johor and the Klang Valley are lifting load quickly, so several extra gigawatts are on the drawing board at TNB and the Energy Commission.
Quick summary
- Malaysia has three grids, run by TNB (peninsula), SESB (Sabah) and SEB (Sarawak).
- Peninsular chain: generators (IPPs and TNB), then the Single Buyer, the GSO, TNB’s networks, with the Energy Commission as regulator.
- Most power comes from coal and gas, except in hydro-based Sarawak.
- Base tariff: 45.40 sen/kWh under RP4 (2025–2027); fuel adjustment turned monthly in July 2025.
- Cooling is where most households can cut their bill; air conditioning and cooling energy has tips.
Calculators related to this topic
Frequently asked questions
Which utility sells me electricity in Malaysia?
What does the Single Buyer actually do?
What is the 2025–2027 base electricity tariff?
What does AFA mean on my TNB bill?
What fuels Malaysia's power stations?
Is it possible for a Malaysian company to buy green power directly?
Sources & references
The figures in this guide are typical ranges taken from the listed sources, and your own values will vary with location, prices and equipment. For estimates specific to your site, use the linked calculators.