Power is a hard commodity to trade. Storing it costs a lot, supply has to match demand second by second, and the wires carrying it can only take so much. No two countries solved this the same way. One extreme is a single state utility doing everything. The other is a 15-minute auction with hundreds of competing generators, and plenty of systems sit in the middle. What your bill looks like, how quickly new plants appear and who pays when fuel prices jump all depend on that choice. Below, the main models come first, then the contracts built on top of them. For the reasons behind negative prices and spikes of hundreds of euros per MWh, go to Why Electricity Prices Spike.
Industry models side by side
| Model | Who owns what | How plants get paid | Examples |
|---|---|---|---|
| Vertically integrated utility | One company generates, transmits, distributes and sells | Regulated tariffs set by the government or regulator | Much of the US south-east, many developing countries, Sarawak |
| Single buyer | Independent power producers (IPPs) build plants; one buyer purchases all output | Long-term PPAs with the single buyer | Peninsular Malaysia, Thailand (EGAT), Vietnam (EVN) in transition |
| Liberalised (competitive) market | Generators and retailers compete; grid is a regulated monopoly | Wholesale market prices plus contracts | EU, Great Britain, Australia NEM, Texas, PJM |
Reform has mostly run from the first model toward the third since the 1990s. The pioneers were Chile (1982), England and Wales (1990) and Norway (1991). A lot of Asian countries stop at the single buyer, because private capital enters generation, yet consumers never see daily price swings.
Example of a single buyer: Malaysia
In Peninsular Malaysia the Malaysia Electricity Supply Industry Reform framework reshaped the sector, and the regulator is the Energy Commission. Two bodies stand out. The Single Buyer contracts power from TNB’s own plants and from IPPs through long-term PPAs, scheduling them at least cost. Real-time dispatch belongs to the Grid System Operator. The grid itself is TNB’s, and customers pay regulated tariffs that are reviewed under the Incentive-Based Regulation framework.
That rigid picture is changing. Firms can now agree virtual PPAs with solar developers under the Corporate Green Power Programme, and in 2024 the ENEGEM cross-border renewable energy exchange started selling green electricity to Singapore. Third-party grid access is under discussion. Sabah and Sarawak operate separate systems. The complete picture is in How Malaysia’s Electricity System Works.
One hour of power, many trades
Where markets are competitive, a single hour of electricity changes hands several times before it is generated.
| Market | When | What happens |
|---|---|---|
| Forward and futures | Years to days ahead | Hedging: generators and retailers lock in prices (EEX, Nasdaq, ASX) |
| Day-ahead | Noon the day before | Auction sets a price for each interval of the next day |
| Intraday | Up to minutes before delivery | Continuous trading and auctions to adjust positions as forecasts change |
| Balancing / real time | Delivery | System operator corrects remaining imbalances, charges those who deviated |
Across Europe, day-ahead markets are linked by one algorithm, SDAC, which sets prices for most of the continent in a single run while respecting cross-border capacity. Its intervals changed from one hour to 15 minutes in October 2025. The auctions are run by exchanges including EPEX SPOT and Nord Pool, and the SIDC platform handles intraday trades between countries.
Hardly any power is bought spot. Generators and retailers fix most of their volumes in advance with forward contracts, so a spot spike lands on company balance sheets before it reaches a household bill. This lag explains why European tariffs climbed during 2022 and fell only gradually in 2023–2024.
Where the grid is the constraint: nodal against zonal
Cheap wind in the north is no use if the lines to southern cities are full. Pricing is the tool that tells the market so.
- Nodal pricing (locational marginal pricing, LMP) prices every one of thousands of network nodes separately, counting congestion and losses. It is used in ERCOT, CAISO, New Zealand, Singapore and PJM, which covers about 65 million people in 13 US states plus Washington DC.
- Zonal pricing means a single price for every bidding zone. Germany and Luxembourg make up one zone although the north–south grid is heavily congested, whereas Italy, Norway, Sweden and Denmark are each divided into several. Congestion is then handled after the auction by paying plants to alter output, called redispatch, which costs Germany billions of euros yearly.
In July 2025, after its Review of Electricity Market Arrangements looked at nodal and zonal options, Great Britain decided to stay with one national price.
Who pays for backup: energy-only or capacity markets
Consider a standby plant that runs for 50 hours a year. Two approaches exist for keeping it in business.
Energy-only markets allow scarcity prices high enough to repay fixed costs. ERCOT in Texas caps real-time prices at US$5,000/MWh; the limit was US$9,000 until the February 2021 crisis. The NEM in Australia has a market price cap above AU$17,000/MWh and settles in five-minute steps.
Capacity markets instead pay per MW for a commitment to be available years in advance, on top of whatever the plant earns from energy. Great Britain, Italy, Poland, Ireland and PJM have them. PJM’s 2025/26 auction cleared at about US$270 per MW-day, nearly nine times the year before, an indication of tight supply as data centres took more power. How they work is spelled out in the capacity market glossary entry.
Contracts that back new plants
Lenders rarely back a 25-year asset against spot prices, so contracts carry most new generation:
- Utility PPAs. For 15–25 years a utility or single buyer pays an agreed price, often linked to inflation. The Large Scale Solar auctions in Malaysia work like this.
- Corporate PPAs. Amazon, Microsoft and Google are among companies contracting directly with wind and solar projects, and BloombergNEF has counted them among the biggest corporate buyers in recent years.
- Contracts for difference. The government side tops up the generator when the market is below the strike price and takes back the surplus when it is above. CfD auctions have been held in the UK since 2014; the EU market reforms agreed in 2024 make the two-sided version standard for new public support.
Strike £80/MWh, market £60 → generator receives £60 + £20 top-up = £80 Strike £80/MWh, market £150 → generator receives £150 − £70 payback = £80
A PPA’s value can be tested in the PPA price calculator, and returns on a whole project in the NPV and IRR calculator.
Retail choice
In a fully open market the household picks the supplier. That is possible in Great Britain, Texas, Australia and most of the EU. Results are mixed. Changing supplier can cut costs, but around 30 small UK suppliers collapsed in the 2021–2022 gas crisis after selling fixed tariffs they had not hedged. Regulators tightened capital and hedging requirements in response, and some markets, Great Britain with Ofgem’s cap among them, now combine competition with price caps.
What to remember
- Models range from one integrated utility to full competition, with Malaysia in the single buyer category.
- Power is traded from years ahead down to real time, and the day-ahead auction sets the benchmark price.
- Nodal prices mirror grid limits directly. Zonal prices are easier but need expensive redispatch.
- Contracts such as PPAs and CfDs, not the spot price, pay for most new plants.
Country-by-country wholesale and retail prices are on the electricity prices page. Behind each market stands a generation mix, which the world energy map displays.
Calculators related to this topic
Frequently asked questions
What does a liberalised power market mean?
How does Malaysia's single buyer model work?
Nodal or zonal pricing: which is which?
PPA meaning: what is a power purchase agreement?
What is a CfD in electricity?
Why do markets pay for capacity?
Sources & references
The figures in this guide are typical ranges taken from the listed sources, and your own values will vary with location, prices and equipment. For estimates specific to your site, use the linked calculators.