Malaysia NETR: 2050 Energy Transition Targets Explained

Malaysia's energy transition plan in brief: 70% renewable capacity by 2050, coal exit by 2044, Solar ATAP, CRESS, hydrogen and what it all costs.

Updated 5 min read 1,262 words

Malaysia exports oil and gas, and its electricity has long come mostly from coal and gas. The National Energy Transition Roadmap (NETR) of 2023 is the government’s plan to change that: renewables should make up 70% of power capacity by 2050, no new coal plants will be built, and new rules apply to solar buyers, drivers and industry. Below you will find what the plan contains, what has happened since and what it means for homes and companies.

Related pages Link
Energy hub Malaysia energy hub
Power system Malaysian electricity page
Country data Malaysia country profile

Starting position

Nine-tenths of primary energy is fossil, as natural gas, oil and coal, according to the Energy Commission handbook and Energy Institute data. Electricity looks like this in Our World in Data’s 2025 figures, which build on Ember and Energy Institute:

Source Share of Malaysian electricity (approx.)
Coal ~45%
Natural gas ~34%
Hydropower ~17–18%
Solar ~2%
Bioenergy and other ~1%

Sarawak, whose grid is mostly hydro, holds most of the hydropower; the peninsula depends on coal and gas. Power generation emitted about 600 g CO₂/kWh in 2025, compared with a world average near 460 g. The carbon intensity guide carries the latest value.

Two phases, one set of targets

Phase Date Content
Phase 1 27 July 2023 Ten flagship catalyst projects and initiatives
Phase 2 29 August 2023 Targets, 2050 pathways and enablers such as financing and regulation
Target 2025 2035 2050
Renewable share of installed capacity 31% 40% 70%
Coal No new plants Coal capacity halved Fully retired by 2044
Energy efficiency Savings in industry, buildings and transport under the new EECA
Emissions Net-zero greenhouse gas emissions as early as 2050 (national pledge)

Every figure above is a share of capacity, not of energy. A Malaysian solar plant runs at a capacity factor of about 15–17% and gas or coal plants at 50–80%, so a 70% capacity share would supply well below 70% of the electricity.

The ten flagships

Phase 1 arranged them under six levers. This is the 2023 outline; individual projects have been revised since.

# Flagship What it covers
1 Energy efficiency Government buildings, industry and households, backed by the new law
2 Renewable energy zones Industrial parks with a dedicated green power supply
3 Hybrid hydro-floating solar Up to 2,500 MW of floating solar on hydro reservoirs
4 Residential solar Rooftop push, now delivered through Solar ATAP
5 Energy storage Batteries to firm up solar on the grid
6 Green hydrogen Sarawak-led H2biscus and H2ornbill, aimed at export to Japan and Korea
7 Hydrogen-based generation Co-firing hydrogen and ammonia in existing plants
8 Future mobility EV charging, public transport, EV uptake
9 Biomass and biofuels Co-firing and sustainable aviation fuel from palm residues
10 Carbon capture, utilisation and storage Petronas’s Kasawari CCS off Sarawak; plans to store CO₂ from other countries

Solar: ATAP, LSS and CRESS

Solar carries more of the 70% goal than any other technology, through three channels.

Channel How it works
Rooftop (Solar ATAP) Replaced the three versions of net energy metering (NEM, 2016 to mid-2025) on 1 January 2026, under an Energy Commission guideline. Self-consumed power avoids the full tariff (energy, capacity and network charges). Exports are credited at the energy charge rate alone for homes and at the average system marginal price for businesses. Unused credit lapses at month-end; contracts run up to 10 years.
Large Scale Solar (LSS) Tenders since LSS1 in 2016 have produced several gigawatts of solar farms. LSS5 (2024), the largest round yet, offered 2,000 MW, and more have followed. Winning bids are among the cheapest new generation in Malaysia.
CRESS Launched September 2024, applications from 30 September 2024. A company agrees a deal with a developer and pays a system access charge to use the TNB grid. Aimed at data centres, semiconductor makers and exporters under customer pressure for green electricity.

Because unused credit disappears, size a rooftop system for daytime use. Run the numbers in the net metering calculator; the scheme’s rules are set out in Solar ATAP and rooftop solar.

Cross-border trade opened as well. Malaysia ended its ban on renewable power exports in 2023, and Energy Exchange Malaysia (ENEGEM) went live at the close of the year, with Singapore as its first customer through the existing interconnector.

Worked example: what 70% of capacity could look like Assume a 2050 system of 60 GW, 70% renewable (42 GW) If 30 GW is solar at CF 16%: 30 × 8,760 × 0.16 ≈ 42 TWh If 8 GW is hydro at CF 45%: 8 × 8,760 × 0.45 ≈ 32 TWh If 4 GW is bio/other at 60%: 4 × 8,760 × 0.60 ≈ 21 TWh Renewable generation ≈ 95 TWh Illustrative numbers only; they show why capacity share ≠ energy share.

Coal, gas, hydrogen and Sarawak

Coal ends in stages. No new units will be built, and the existing fleet retires as its power purchase agreements run out, with half the capacity gone by 2035 and the rest by 2044. That is firmer than the NETR’s first projection of a near-complete exit by 2045. In the medium term, much of the gap should be filled by gas, including new combined-cycle plants. Looking further out, the options are carbon capture and co-firing with hydrogen or ammonia.

Sarawak follows a separate path. Its state utility SEB operates two big dams, Bakun (2,400 MW) and Murum (944 MW). The state is also pursuing export-oriented green hydrogen and hydrogen buses in Kuching, and plans a subsea cable to Singapore. Some of its power already reaches West Kalimantan, Indonesia.

Efficiency law

The Energy Efficiency and Conservation Act 2024 (EECA) took effect on 1 January 2025. Large consumers above a regulated threshold must appoint energy managers, report their consumption and be audited. Labelling rules for air conditioners, fridges and similar appliances get tougher too, and air conditioning and cooling energy covers the cooling side.

Transport and subsidy reform

Roughly one-third of final energy goes to transport, much of it subsidised RON95 petrol and diesel. To shift this, the NETR promotes EVs with a target of 10,000 public charging points by 2025, and EV shares of new car sales of 15% in 2030, 38% in 2040 and 80% in 2050. Fuel subsidy changes move in step:

Date Change
10 June 2024 Diesel in Peninsular Malaysia floated (RM2.15 to RM3.35 a litre)
30 September 2025 BUDI95: RON95 at RM1.99 a litre for citizens, within a 300-litre monthly quota
1 July 2026 BUDI Diesel at RM2.10, nationwide
Topic Page
Why subsidies matter fossil fuel subsidies explained
Today’s pump prices Malaysia fuel prices

Cost and financing

The pathway chosen decides the bill, which ranges from RM435 billion to RM1.85 trillion by 2050 and goes mainly to renewables and grids. Private investors, utilities and development banks are expected to supply the bulk; the National Energy Transition Facility provides only seed capital.

Practical implications

Who What changes
Households ATAP pays best when panels match daytime use; efficient air conditioning is the largest saving
Businesses CRESS and green tariffs provide certified renewable power; EECA brings audits for large users
The grid More solar needs storage and interconnection, including the ASEAN Power Grid
Keep reading Page
The system today how Malaysia’s electricity system works
The region energy in Southeast Asia

Targets are set on capacity, so also follow actual generation data, which arrives later.

Calculators related to this topic

Frequently asked questions

When was Malaysia's NETR published, and what is it?
It is the National Energy Transition Roadmap, the government's plan for moving the energy system toward net zero. The Ministry of Economy released it in two parts: ten flagship catalyst projects on 27 July 2023 (Phase 1), then targets and pathways to 2050 on 29 August 2023 (Phase 2).
How much renewable energy is Malaysia aiming for?
There are three capacity milestones: 31% in 2025, 40% in 2035 and 70% by 2050. Note that these count installed capacity rather than electricity produced, and large hydro dams are counted in.
What is Malaysia's coal phase-out date?
The NETR bans new coal plants. Officials have since set a goal of halving coal capacity by 2035 and closing the rest by 2044, retiring plants as their power purchase agreements end. Real progress depends on gas, renewables and storage coming online fast enough.
Which scheme replaced NEM for rooftop solar?
Solar ATAP, short for Solar Accelerated Transition Action Programme. TNB customers in Peninsular Malaysia could join from 1 January 2026, once NEM 3.0 had shut in mid-2025. A home's exports earn the energy charge rate only (no capacity, network or AFA components), a business's the average system marginal price. A credit can only cancel imports in the same billing month.
What is CRESS and who is it for?
The Corporate Renewable Energy Supply Scheme, live since 2024, lets a company contract electricity directly from a renewable developer. Delivery runs over TNB's grid, and the company pays a system access charge. Typical users are data centres and manufacturers who must show that their power is green.
What price tag does the NETR carry?
Depending on the scenario, RM435 billion up to RM1.85 trillion by 2050. Private firms are expected to put in the larger part, and the government contributes seed money via vehicles like the National Energy Transition Facility.

Sources & references

  1. Ministry of Economy Malaysia: National Energy Transition Roadmap (NETR)
  2. Suruhanjaya Tenaga: Malaysia Energy Statistics Handbook
  3. Sustainable Energy Development Authority (SEDA): Solar ATAP and RE programmes
  4. Ministry of Energy Transition and Water Transformation (PETRA): CRESS
  5. Ember: Malaysia electricity data / Our World in Data

The figures in this guide are typical ranges taken from the listed sources, and your own values will vary with location, prices and equipment. For estimates specific to your site, use the linked calculators.