Where Southeast Asia gets its power: fast demand growth, heavy fossil use, the Indonesia and Vietnam JETPs, Vietnam's solar boom, Lao hydro and ASEAN grid links.

Updated 6 min read 1,334 words

Eleven countries and about 690 million people make up Southeast Asia, and demand for energy there is climbing faster than in most places. Manufacturers are leaving China, cities keep spreading, and millions of households are buying a first air conditioner or motorbike. Through 2035, about a quarter of all growth in world demand is expected to come from here, per the IEA. Fossil fuels still supply most of it. Meeting that demand with coal and gas, or with solar, wind and hydro, will shape air quality, regional economies and the global climate, and the sections below take it country by country.

For Malaysia Page
Regional context ASEAN hub
Transition plan Malaysia’s NETR

The region in numbers

What the IEA’s 2024 outlook for the region found:

Indicator Finding
Energy demand Up about 3% a year over two decades
Electricity demand About 6% a year in the 2000s, easing to about 4% a year lately
Fossil share of demand About 80%; oil dominates transport, coal and gas dominate power
Coal-fired generation More than doubled since 2010, now close to half of regional electricity
Clean energy spending About USD 30 billion a year, far below what the climate pledges need
Emissions outlook Energy-related CO₂ keeps rising into the 2030s under stated policies
Country Electricity mix (approx., 2023–2024) Remark
Indonesia Coal ~60%, gas ~15–18%, hydro ~7%, geothermal ~5% Biggest economy and emitter in the region
Vietnam Coal ~48%, hydro ~33%, solar and wind ~12% (2025) Largest solar and wind fleet in ASEAN
Thailand Gas ~65% of generation, coal ~18%; net imports (mostly Lao hydro) ~16% of demand Relies on Gulf of Thailand gas and LNG
Philippines Coal ~60%, gas ~15%, geothermal ~8%, hydro ~5–8% Retail power prices are high
Malaysia Coal ~45%, gas ~34%, hydro ~17%, solar ~2% (2025) Sarawak runs mostly on hydro
Singapore Gas ~95% Aims to import up to 6 GW of low-carbon power by 2035
Laos Hydro ~70–75%, coal (Hongsa) ~25% Sells most of its electricity abroad
Note
Source Ember and Our World in Data, rounded
Newest year world energy map

Coal keeps growing

Coal plants in this region are young. A wave of tens of gigawatts went up in Indonesia, Vietnam and the Philippines during the 2010s, leaving a typical unit about 15 years old, compared with over 40 in the US and Europe. Shutting one down early means paying its owners for decades of revenue they will never earn, and that is why transition money is aimed at coal first.

Indonesia is the world’s top coal exporter, shipping about 500 million tonnes a year, mostly to China, India and other Asian buyers. A rising share is burned at home in captive power plants within industrial parks, which feed the nickel smelters of Sulawesi and Halmahera. CREA put this captive capacity above 10 GW in 2023, with more being built. The country produces over half the world’s nickel, largely for EV batteries, so a slice of that low-carbon supply chain presently runs on coal.

If you want to know Read
Where battery metals come from critical minerals for energy
How a plant turns coal into power coal types and how a coal plant works

JETPs: paying to exit coal

Indonesia Vietnam
Announced November 2022 December 2022
Pledged USD 20 billion, public and private, led by the US and Japan USD 15.5 billion from G7 countries and partners

Both aim to bring the peak of power-sector emissions forward and to retire coal plants ahead of schedule.

Neither has delivered on time. Most funds are loans at near-market rates, grants are marginal, and nobody has found it easy to design early-retirement deals. In March 2025 the US pulled out of both, while the other partners stayed. Indonesia’s Cirebon-1 coal plant became the pilot case for early retirement under the Asian Development Bank’s Energy Transition Mechanism.

Gas and LNG imports

After coal, gas is the next biggest fuel here. Exporters of LNG for many years include Malaysia, Indonesia and Brunei. Four others, Thailand, Singapore, the Philippines and Vietnam, now buy it abroad because their own fields are in decline. Thailand shows the pattern best. Its Gulf of Thailand fields are fading, LNG fills the gap, and LNG prices swing, as consumers learned when Asian spot prices shot up in 2022.

Topic Guide
How cargoes move LNG value chain explained
What the gas costs how gas prices are set

Renewables: strongest where policy pays

Vietnam is the example of what generous policy can do. Solar was paid 9.35 US cents/kWh in 2019 and rooftop systems 8.38 cents in 2020. By the end of 2020 about 16 GW stood installed, against almost none two years earlier; roughly 9 GW of it sat on rooftops, every watt built in 2020. Lines could not keep up, so output was curtailed, and investors faced unsettled rules for years. In its 2025 revision, Power Development Plan 8 (PDP8) schedules large volumes of solar, onshore and offshore wind and LNG power, and it brings nuclear back.

Geothermal. Ranked by capacity, the US is first, Indonesia second at about 2.6 GW and the Philippines third at about 1.9 GW. How it works: Geothermal Energy Explained.

Hydropower. Laos has put dozens of dams on the Mekong and its tributaries, more than 10 GW in total. Thailand is the main customer. Vietnam, Cambodia and (via LTMS) Singapore get less. Export income is the upside of the “battery of Asia” plan. The downside is debt, much of it owed to Chinese lenders, plus concern about Mekong fish stocks and sediment. Background: Hydropower Explained.

Solar elsewhere. Auctions in Malaysia, Thailand and the Philippines make projects compete on price. Irradiation of 1,400–1,800 kWh/m² a year is typical across the region, though cloud cover and limited land cap how much can be built. Pick a site on the solar potential map to see its resource.

Worked example: how much solar replaces one coal unit? Coal unit: 600 MW × 8,760 h × 70% capacity factor ≈ 3,680 GWh a year Solar in Southeast Asia: capacity factor ≈ 15–17% Solar needed for the same energy: 3,680,000 MWh ÷ (8,760 × 0.16) ≈ 2,600 MW Plus storage or other firm capacity for nights and cloudy spells.

To rerun this with your own plant size and capacity factor, use the capacity factor calculator.

Cross-border power: the ASEAN Power Grid

Year Step
1997 ASEAN Power Grid concept launched
Early links Bilateral lines: Malaysia–Thailand, Malaysia–Singapore, Laos–Thailand, Sarawak–West Kalimantan
June 2022 Lao PDR–Thailand–Malaysia–Singapore Power Integration Project (LTMS-PIP) goes live, the first deal with more than two countries
2024 LTMS-PIP renewed and enlarged by its partners

Under LTMS-PIP, up to 100 MW of Lao hydropower crosses the Thai and Malaysian grids and ends up in Singapore.

Singapore is aiming for about 6 GW of imports by 2035. Conditional licences have been issued for low-carbon power from Indonesia, Cambodia, Vietnam and Malaysia, to arrive on long subsea HVDC cables (see transmission and HVDC explained).

Regional targets

Target for 2025 (APAEC 2016–2025) Goal Outcome (ASEAN Centre for Energy)
Energy intensity 32% below 2005 Within reach
Renewables in total primary energy supply 23% About 15–16%; coal and oil use grew too
Renewables in installed power capacity 35% Within reach

These were aspirations rather than commitments. In 2025 ASEAN adopted a successor plan for 2026–2030.

Summary

  • About 80% of the region’s energy is fossil, and demand grows 3–4% a year.
  • Young coal plants make early retirement costly; the JETPs have paid out less than promised.
  • Vietnam showed solar can grow at speed, provided the grid keeps up.
  • Low-carbon strengths of the region: Lao hydro, geothermal in Indonesia and the Philippines, and growing cross-border links.
  • Market prices today: oil and natural gas.

Calculators related to this topic

Frequently asked questions

How fossil-fuel dependent is Southeast Asia?
Very. Per the IEA Southeast Asia Energy Outlook 2024, oil, coal and natural gas together meet roughly 80% of regional energy demand. Coal grew fastest within power generation, with Indonesia, Vietnam and the Philippines in the lead.
What is a JETP and how does it work?
It is a funding bargain: richer governments and lenders back a developing country that agrees to retire coal sooner. Indonesia's package of November 2022 totals USD 20 billion, Vietnam's of December 2022 USD 15.5 billion. Disbursement has been slow, and in 2025 the United States left both.
Why did Vietnam's solar capacity grow so quickly?
Pricing did it. Feed-in tariffs of 9.35 US cents per kWh (2019) and 8.38 cents (2020) set off a building rush, taking solar from near zero in 2018 to about 16 GW by 2020. Roughly 9 GW was rooftop, all installed during 2020. Wires could not carry that much power, hence the curtailment that followed.
Why is ASEAN building a regional power grid?
The idea is to tie member countries' networks together with cross-border lines, pair by pair at first and later as a single connected system. Its first multi-country trade, LTMS-PIP, has carried Lao hydropower through Thailand and Malaysia to Singapore since June 2022.
Who leads Southeast Asia in geothermal power?
Indonesia, with about 2.6 GW, ranks second worldwide behind the United States. Next comes the Philippines at about 1.9 GW.
Were ASEAN's 2025 renewable energy goals achieved?
Only partly. Targets stood at 23% renewables in primary energy supply and 35% in power capacity. Capacity landed near its mark; in the ASEAN Centre for Energy's newest data the primary share is just 15 to 16%.

Sources & references

  1. IEA (2024). Southeast Asia Energy Outlook 2024
  2. ASEAN Centre for Energy: ASEAN Energy Outlook and APAEC progress reports
  3. Ember: Southeast Asia electricity data
  4. Energy Institute: Statistical Review of World Energy 2025
  5. Centre for Research on Energy and Clean Air (CREA): Captive coal in Indonesia's nickel industry

The figures in this guide are typical ranges taken from the listed sources, and your own values will vary with location, prices and equipment. For estimates specific to your site, use the linked calculators.