Real, reactive and apparent power
An AC circuit carries two kinds of power. Real (active) power, in kW, is the part that does work, such as heat, light or motion. Reactive power, in kVAr, flows back and forth to magnetise motors and transformers and delivers no net work. Combine the two as vectors and you get apparent power, in kVA, which sets the current that cables, switchgear, transformers and generators have to carry. Divide kW by kVA to get the power factor (cos φ).
Type in the quantity you know (kVA, kW or current) plus the power factor, the system type (single-phase, three-phase or DC) and the voltage. You get the rest back, a drawn power triangle, a view of current climbing as power factor drops, and the size of capacitor bank that corrects the power factor to your target.
Formulas
Example: sizing up a 100 kVA generator
The preset is a three-phase generator of 100 kVA at 400 V, with the usual rating power factor of 0.8:
- Real power is 100 × 0.8 = 80 kW.
- Reactive power is 100 × sin(36.9°) = 60 kVAr.
- Current is 100,000 ÷ (1.732 × 400) = 144 A per phase.
Suppose the site’s load really sat at PF 0.8. A 33.7 kVAr capacitor bank would raise it to 0.95, and the same 80 kW would need only 84.2 kVA and 122 A. Current falls 16%, cable losses about 29% (they follow current squared), and 16 kVA of generator or transformer capacity is freed.
Interpreting the charts
- Power triangle: kW along the base, kVAr up the side, kVA as the sloping edge. The dashed line is the corrected kVA, with kW unchanged and a shorter hypotenuse.
- Current versus power factor: for the same useful power, current climbs sharply below PF 0.8, and that is what utilities penalise.
- Standard sizes table: kW and amps for common generator and transformer ratings at PF 0.8 and your voltage.
Typical power factors
- 1.00: resistive heaters, kettles, incandescent lamps.
- 0.95–1.00: EV chargers, modern power supplies with PFC, PV inverters.
- 0.90–0.98: LED lighting with quality drivers.
- Induction motors: 0.80–0.90 at full load, 0.65–0.80 at half load, 0.20–0.40 with no load.
- 0.50–0.70: welding transformers and arc furnaces.
- 0.70–0.85: a typical industrial site before correction.
Current at common ratings (three-phase)
Each line gives kVA, then kW at PF 0.8, then amps at 400 V, 480 V and 208 V:
- 20 kVA: 16 kW; 29 A, 24 A, 56 A.
- 50 kVA: 40 kW; 72 A, 60 A, 139 A.
- 100 kVA: 80 kW; 144 A, 120 A, 278 A.
- 250 kVA: 200 kW; 361 A, 301 A, 694 A.
- 500 kVA: 400 kW; 722 A, 601 A, 1,388 A.
- 1,000 kVA: 800 kW; 1,443 A, 1,203 A, 2,776 A.
Practical points
- Size generators for kVA and for starting current. A motor can pull 3–7 times its running current at start; soft starters and VFDs cut that.
- Correct at the source. Capacitors on large motors reduce current throughout the distribution system, not only at the main board.
- Avoid over-correction. At light load a leading power factor can raise voltage; automatic stepped banks prevent this.
- Look at harmonics. Variable-speed drives distort current, and plain capacitors may resonate with the network, so use detuned reactors.
- For balanced three-phase loads with star/delta detail, go to the three-phase power calculator.
Limits of the calculation
It assumes sinusoidal voltage and current and a balanced three-phase load. Non-linear loads bring harmonic distortion into the “true power factor”, and capacitors do not cure that. Breaker, cable and capacitor sizing must follow local wiring rules and manufacturer data.
Method & assumptions
The power triangle gives S² = P² + Q², with P = S · cos φ and Q = S · sin φ. Line current: I = S ÷ V for single-phase and I = S ÷ (√3 · VLL) for three-phase. A capacitor for correction supplies Qc = P · (tan φ1 − tan φ2). Since cable losses grow with I², lifting the power factor from 0.8 to 0.95 trims them by roughly 29%.
Frequently asked questions
What is the formula to turn kVA into kW?
How do I get from kW to kVA?
What current does 100 kVA draw?
Why do generator labels show kVA and not kW?
What power factor counts as good?
How do I size a power factor correction capacitor?
Sources & references
Embed this calculator
Free for bloggers, installers, schools and NGOs. Copy the snippet below and it stays current by itself.