Glossary · Grid & markets

Merit order

Plants lined up by rising marginal cost so the cheapest run first; the last one needed sets the market clearing price.

The merit order is how an electricity market's supply curve is built. Plants queue by short-run marginal cost (fuel, carbon, variable operation and maintenance), lowest first, and run in that order until demand is met. In a uniform-price (pay-as-clear) auction, the final plant called sets one price for all accepted bids.

Take a European example, cheapest first. Wind, solar and run-of-river cost almost nothing per extra MWh. Next come nuclear (fuel about 5 to 10 EUR/MWh), lignite, hard coal, combined-cycle gas, open-cycle gas and oil. A gas plant's short-run cost is approximated by:

SRMC = (Fuel price / Efficiency) + (Emission factor × Carbon price / Efficiency) + Variable O&M

Example: a CCGT with 55% efficiency, gas at 35 EUR/MWhth and EU ETS carbon at 70 EUR/t (0.2 t CO₂/MWhth) comes to about 64 + 25 + 3 ≈ 92 EUR/MWh.

Bring in more renewables at zero marginal cost and the curve shifts to the right, so dear plants drop out and wholesale prices ease. This is the merit-order effect; studies on Germany found savings of roughly 5 to 10 EUR/MWh in the 2010s. When gas became the price-setter in the 2022 crisis, fuel costs fed into every unit of power, and the EU began debating market design reform. Related: negative prices.

Related terms

All terms →
  • Day-ahead market

    Auction on the preceding day in which wholesale power is traded, producing hourly or 15-minute prices and the generation schedule for the next day.

  • Negative electricity prices

    Wholesale electricity priced under zero: generators pay to feed in because supply that cannot ramp down exceeds demand.

  • Carbon price

    Charge levied on every tonne of CO2e released, whether by carbon tax or emissions trading, so that damage from emissions is reflected in market prices.

  • Dispatchable generation

    Generation that the operator can schedule, ramp up or turn down on demand, whatever the weather.

  • Heat rate

    Fuel energy a thermal plant has to burn per kWh of electricity delivered; it is efficiency turned upside down, typically stated in BTU/kWh or kJ/kWh.

  • OPEX

    OPEX, or operating expenditure, is what it costs each year to operate and maintain an energy asset, from fixed charges per kW-year to variable ones per MWh.