How fast a generator or other resource can move its output up or down, expressed in MW per minute or as a share of capacity per minute.

Rough ramp rates by technology: open-cycle gas turbines and reciprocating engines manage 10–20%/min or more. Combined-cycle plants do 2–8%/min, coal 1–4%/min, hydro more than 20%/min, and nuclear plants built for load following about 1–5%/min within limits. Batteries respond at essentially 100% in under a second.

Growing wind and solar make net load change quickly, and that is why ramping speed counts for more every year. See baseload, peaking and flexibility.

Related terms

All terms →
  • Net load

    What is left of electricity demand after variable wind and solar generation is taken off, which dispatchable plants, storage and imports must supply.

  • Minimum stable load

    The lowest output at which a thermal plant can keep running without tripping offline, often 25–50% of rated capacity.

  • Load following

    Raising or lowering a power plant's output over minutes to hours so it follows electricity demand or the swings of variable renewable generation.

  • Open-cycle gas turbine (OCGT)

    A simple-cycle gas turbine venting hot exhaust straight to the air: efficiency is low (33–42%), but it starts quickly and costs little to build, so it mostly serves peaks.