Beyond simple payback
Plenty of online tools give you one payback number and stop. People who fund plants look elsewhere: at yearly cash after opex, tax and loan repayments, and at the net present value, internal rate of return and debt service coverage ratio that come out of it. What you have here is a small-scale version of the project-finance spreadsheets used for solar parks, wind farms and thermal plants.
Inputs fall into three groups. The plant: capacity, capacity factor, degradation, life. The economics: capex, fixed and variable opex with escalation, the electricity price with its own escalation, residual value. The financing: gearing, interest rate, tenor, tax rate, depreciation period, cost of equity and WACC. From these the tool produces a cash-flow statement and then reports:
- Equity IRR and equity NPV, measured at your cost of equity (the sponsor’s view);
- Project IRR and project NPV, measured at the WACC (the asset’s view, before financing);
- Minimum and average DSCR, to judge whether a bank would lend;
- Equity payback and LCOE.
Calculation steps
Sample run: 20 MW of solar
Out of the box the calculator describes a 20 MW park with a 15% capacity factor, which is 26,280 MWh in year 1. It costs 13 million to build (650,000 per MW) and carries 260,000 of annual opex that grows 2.5% a year. Output sells at 65 per MWh, with the price climbing 1.5% yearly. The loan covers 70% of cost at 6% for 15 years; tax is 20% and depreciation is straight-line over 20 years.
Results for year 1: 1.71 million revenue and 1.45 million EBITDA, an 85% margin. Debt comes to 9.1 million and costs about 937,000 a year to service, so the minimum DSCR is 1.49. The project IRR is about 9.2%, giving a project NPV near +3.5 million at a 6.5% WACC. Shareholders put in 3.9 million and earn an equity IRR of about 14.1%; at a 10% cost of equity the equity NPV is roughly +1.75 million. They get their money back after about 8.3 years, and LCOE is near 55 per MWh.
The verdict reads “bankable”: the equity return clears the 10% hurdle and DSCR stays far above the 1.20–1.35 range lenders look for. Lower the price to 55 per MWh, though, and minimum DSCR falls to 1.25 while equity IRR drops to about 9.3%. That misses the hurdle, so equity NPV turns negative while project NPV remains positive.
Interpreting the numbers
- Compare equity IRR with your cost of equity. Higher means positive equity NPV.
- Compare project IRR with WACC. A big equity IRR sitting on a weak project IRR will not hold up well.
- A DSCR under 1.2 in any year hints that a lender would reduce the loan or lengthen the tenor.
- In the cash-flow chart, each year’s revenue is split between opex, tax, the lender and shareholders.
Typical financing terms
| Item | Contracted (EU/US) | Merchant or emerging |
|---|---|---|
| Gearing | 65–80% | 40–60% |
| Debt tenor | 15–20 years | 7–12 years |
| Interest rate (all-in) | 4–7% | 7–12% |
| Minimum DSCR | 1.20–1.30 | 1.40–1.75 |
| Cost of equity | 7–10% | 12–20% |
| Corporate tax | 15–30% | 15–35% |
Hints for better runs
- Run the bad case. Lenders size debt on a P90 energy yield (−5 to −10% capacity factor) and a weaker price, so try both.
- Do not let the loan outlive the PPA. Any gap exposes repayments to merchant prices.
- Put everything in capex. That means grid connection, development fees and contingency. Equity absorbs overruns first.
- Model the tax shield. If accelerated depreciation applies where you build, shorten the depreciation period; equity IRR goes up.
- Sanity-check with LCOE. A price below LCOE at your WACC means a negative project NPV.
What is left out
Yearly steps, an annuity loan, a single price curve. No construction phase, no debt sizing or sculpting, no reserve accounts, VAT or working capital. Professional models work semi-annually, sculpt debt to a DSCR target and include P50/P90 cases, curtailment and balancing costs. Use this page to screen ideas and to learn, and get a full model built before any money is committed.
Method & assumptions
Each year is built up as follows. Energy: MW × 8,760 × CF × (1 − degradation)t−1 (CF being capacity factor). Revenue: energy times a price that rises with escalation. EBITDA: revenue less fixed opex (escalating) and variable opex. The loan accrues interest on its balance while an annuity amortises it over the tenor. Taxable income: EBITDA − depreciation − interest, with losses carried forward; cash to equity: EBITDA − tax − debt service.
Discount the flows with NPV = Σ CFt ÷ (1 + r)t; IRR is the rate r at which NPV = 0, solved by bisection. At the WACC, LCOE = PV(capex + opex) ÷ PV(energy).
Frequently asked questions
Project IRR vs equity IRR: how do they differ?
Which IRR is considered healthy for solar and wind?
What does DSCR mean and which level do lenders want?
How is NPV calculated for an energy project?
Should the discount rate be real or nominal?
Why do equity cash flows step up late in the project life?
Sources & references
- IRENA (2024). Renewable Power Generation Costs in 2023 — cost of capital and financing assumptions
- NREL — System Advisor Model (SAM): financial models documentation
- IEA (2024). Cost of Capital Observatory
- Yescombe, E.R. & Farquharson, E. (2018). Principles of Project Finance, 2nd ed. Academic Press