Capacity market
A scheme that pays resources for standing ready to supply power or cut demand during system stress, on top of payments for energy.
Under a capacity market the payment goes to firm capacity (MW) from generators, storage and demand-side resources, not to the energy (MWh) they deliver. The purpose is to secure resource adequacy where energy-only prices could leave rarely run plants unable to recover fixed costs, known as the missing money problem.
The usual sequence: the system operator projects peak demand and adds a reserve margin, then runs one central auction years ahead. Each participant's volume is scaled by its capacity credit; Great Britain, for example, counts 4-hour batteries at about 60 to 65%, CCGT around 90% and onshore wind below 10%. Winners face penalties if not available when the system is stressed.
Examples:
- PJM (US): the 2025/26 Reliability Pricing Model auction cleared at 269.92 USD/MW-day, almost nine times the prior year, reflecting retirements and rising data-centre demand.
- Great Britain: the 2028/29 T-4 auction cleared at 65 GBP/kW-year.
- Similar schemes exist in Italy, Poland, Ireland, France and Belgium, cleared under EU state-aid rules.
Sceptics argue these mechanisms may over-buy capacity and lock in fossil plants; Texas (ERCOT) uses scarcity pricing under a 5,000 USD/MWh cap instead.
Related terms
All terms →- Reserve margin
How far available or accredited capacity sits above forecast peak demand, given as a percentage of that peak.
- Capacity credit
Share of a resource's nameplate capacity that planners can rely on during peak demand, used in adequacy studies and capacity markets.
- Peak load
The highest electricity demand a grid records over a given period; it fixes the capacity the system has to be able to deliver.
- Demand response
Changes in end users' electricity use, prompted by price signals or operator requests, that help balance the grid.
- Dispatchable generation
Generation that the operator can schedule, ramp up or turn down on demand, whatever the weather.
- Contract for Difference (CfD)
A contract or support scheme that pays a generator the gap between an agreed strike price and a market reference price, and takes money back from it when the market price is higher.