No other part of the wind sector scaled up as quickly. Eleven turbines of 450 kW made up Vindeby (Denmark, 1991), the first offshore farm anywhere. Today’s European and Chinese installations use 14–16 MW machines with rotors wider than 230 m, and some projects exceed 1 GW. The sections below explain why anyone pays extra to build at sea, what is different about the hardware, what yields and costs look like, and where the true limits lie.
Why sea wind beats land wind
Energy in the wind grows with the cube of its speed, so even a small speed advantage pays off heavily. Water offers little resistance: the roughness length is about 0.0002 m for calm sea, against 0.03–0.1 m over farmland and 0.5 m or more over forest. The wind therefore keeps its speed near the surface and varies less with height, and calmer, less turbulent air eases fatigue on blades and drivetrains.
Per square metre of rotor, a 10 m/s hub-height site carries about triple the power of a 7 m/s one. Good North Sea locations see 9–11 m/s; a lot of European land sites average only 6–8 m/s. Try the wind speed at height calculator to see the effect of height and terrain, and look at regional wind resources on the world energy map or at any point in the Energy Explorer.
The payoff shows up in the capacity factor, i.e. actual annual output as a fraction of what the turbine could theoretically produce (what capacity factor means).
| Technology | Typical capacity factor | Notes |
|---|---|---|
| Onshore wind, older fleet | 20–30% | Smaller rotors, lower hubs |
| Onshore wind, new projects | 30–45% | Large rotors relative to generator rating |
| Offshore wind, fixed-bottom | 40–55% | North Sea projects often above 45% |
| Floating offshore (early arrays) | 45–55% | Hywind Scotland posted some of the highest UK factors in its first years |
Sources for these ranges: IEA Offshore Wind Outlook 2019, IRENA cost reports and the NREL Annual Technology Baseline. A windy or calm year can move a figure by several points.
Equipment: turbines, foundations, cables
Turbines
The layout is the same as onshore (three blades, upwind, horizontal axis) just bigger. Each turbine position brings a large fixed cost for foundation and installation, so bigger turbines in smaller numbers save on foundations, cable runs and vessel trips. A public 15 MW reference design with a 240 m rotor and a 150 m hub, released by NREL and IEA Wind Task 37 in 2020, mirrors the machines that arrive in the mid-2020s.
Differences from land turbines:
- Direct-drive or medium-speed generators are popular because repairing a gearbox far from land is costly.
- Salt air calls for sealed, dehumidified nacelles and towers, marine coatings and cathodic protection on the foundations.
- Roads do not limit size. Blades over 100 m long would be nearly impossible to truck but go by ship from factories on the quayside.
Foundations
| Foundation | Typical water depth | How it works |
|---|---|---|
| Monopile | up to ~40–60 m | Single steel tube, 8–11 m diameter for the largest turbines, driven or drilled into the seabed |
| Jacket | ~30–60 m | Steel lattice with three or four legs pinned by piles |
| Gravity base | shallow, firm seabed | Heavy concrete base held down by its own weight |
| Floating spar | 100 m+ | Deep ballasted cylinder, very stable, but needs deep water at the quay too |
| Semi-submersible | ~50 m+ | Three or four columns, assembled in port and towed out |
| Tension-leg platform | ~50 m+ | Buoyant hull pulled down by taut tendons, small footprint |
A quarter or more of a project’s capital often goes on foundations and installation. Monopiles carry most installed capacity today, as they are simple to mass-produce.
Electrical system
Power flows from each turbine through an array cable (66 kV on newer projects, previously 33 kV) to an offshore substation, where the voltage is raised to 132–275 kV for the export cable to shore. Beyond roughly 80–100 km, high-voltage direct current (HVDC) is cheaper than AC, whose cables draw big capacitive charging currents that consume transfer capacity. The catch is the large, expensive converter platforms HVDC needs at sea, so AC versus DC is one of the key choices in design.
Cable faults cost more lost output than their size suggests: a break in the export cable can silence an entire farm for weeks while a repair vessel is arranged. That is why new projects often install two export cables or tie substations together.
Worked example: yearly energy from a 1 GW farm
Picture a North Sea project: 67 turbines rated 15 MW each (1,005 MW in total), with a long-term mean hub-height wind of 10 m/s.
- Gross energy. Weibull wind statistics combined with the power curve give a 15 MW turbine at 10 m/s a gross capacity factor of about 55–60%.
- Wakes. Machines behind others work in slower, choppier air. Wake losses in big arrays often reach 8–15%, and adjacent farms cast “external” wakes on top.
- Availability. Waves restrict crew access, so offshore availability of 93–97% is normal, versus 97–99% on land.
- Electrical losses. Transformers plus array and export cables take 2–4%.
To put 4.2 TWh a year in perspective: Cyprus uses about that much, Estonia about twice as much (see the country profiles). Replacing gas plants emitting roughly 350–400 g CO₂/kWh would prevent around 1.5–1.7 million tonnes of CO₂ yearly. Other grids can be tested in the electricity CO₂ calculator, while the wind turbine calculator applies the same Weibull and power-curve method to one turbine at your own site.
What offshore wind costs
To compare fairly, use the levelised cost of electricity (LCOE), which is total lifetime cost per unit of lifetime output (see LCOE explained). Offshore it is mostly about capital:
| Cost element | Approx. share of lifetime cost | Drivers |
|---|---|---|
| Turbines | 30–40% | Steel and rare-earth prices, turbine OEM margins |
| Foundations and installation | 20–30% | Water depth, soil, vessel day rates |
| Electrical (array, substation, export) | 10–20% | Distance to shore, AC vs HVDC; sometimes paid by the grid operator |
| Operations and maintenance | 20–30% | Distance, weather windows, crew transfer vessels or service operation vessels |
| Development, financing, decommissioning | remainder | Interest rates, consenting time |
Treat the shares as indicative: they vary widely between projects and countries (published breakdowns from NREL ATB and IRENA).
Read headline prices with two warnings in mind:
- Strike prices differ from LCOE. A contract-for-difference price bundles in indexation, grid arrangements and risk premia, none of which are uniform across countries. Britain and Germany handle transmission assets differently, so the very same farm can seem cheaper or more expensive on paper.
- Costs rose after 2021. IRENA documented offshore LCOE falling for most of the 2010s. Then came 2022–2024: interest rates, steel prices and supply-chain bottlenecks all rose, costs climbed again and several US and UK developers cancelled or renegotiated contracts. Since the business is so capital-heavy, a few points of cost of capital shift LCOE substantially: put it into the LCOE calculator and a rise in the discount rate from 5% to 8% typically adds about a quarter.
Floating wind is still a lot dearer than fixed-bottom, since volumes are tiny. NREL’s ATB projects steep falls once arrays reach hundreds of MW, but those are forecasts, not prices anyone has seen.
Strengths and weaknesses
Strengths
- Capacity factors are high and output is steadier than from onshore wind or solar.
- Northern European output is strongest in winter, alongside heating demand, so it pairs well with solar.
- Big sites near coastal load centres compete little for land.
- Industry and ports benefit. The IEA’s 2019 outlook judged technical potential near the coast to be many times global electricity demand.
Weaknesses
- Variability. A calm lasting several days can cover the whole North Sea, so as with any variable source you need backup, interconnectors, storage or flexible demand; see our guide to the power grid for how operators keep supply and demand level.
- Grid connection. Bringing gigawatts ashore frequently needs new onshore lines, and permitting those can take longer than the farm.
- Supply chain. The largest turbines can be lifted by only a handful of vessels, and quay space for assembly is scarce.
- Competing uses of the sea. Ship routes, fishing areas, military zones and radar all rule out parts of the sea.
- Sensitivity to interest rates, as explained above.
Where it is being built
Through the early 2020s, five countries held most installed offshore capacity: China, the UK, Germany, the Netherlands and Denmark; In several recent years China added the most, according to GWEC’s Global Offshore Wind Report. Poland, the Baltic states, Taiwan, South Korea, Japan, Vietnam and the US East Coast are now building their first large farms. Seabed shape matters enormously, and shallow, windy shelves come out on top. Large parts of the North Sea are shallower than 50 m with mean winds near 10 m/s, nearly ideal for fixed-bottom foundations, whereas the US West Coast and the Pacific side of Japan drop off into deep water and depend on floating technology.
The rankings pages show each country’s wind share, and a country profile gives its generation mix over time.
Key takeaways
- In return for higher capital and upkeep costs, offshore wind delivers stronger, steadier wind and net capacity factors of 40–55%, compared with 25–45% on land.
- Fixed-bottom projects now mostly use 14–16 MW turbines on monopiles or jackets, and floating platforms, though still expensive, open deep coastlines.
- How much of the gross resource reaches the grid depends on wakes, availability and cable reliability.
- Because costs fall almost entirely up front, interest rates influence the price of offshore power about as much as turbine technology.
Calculators related to this topic
Frequently asked questions
What is the point of building wind farms at sea if land is cheaper?
What does a single offshore turbine generate in a year?
Fixed-bottom versus floating offshore wind: what is the difference?
What is the lifespan of an offshore turbine?
Does offshore wind cost more than onshore?
What does offshore wind do to marine life?
Sources & references
- IEA (2019). Offshore Wind Outlook 2019
- IRENA — Renewable Power Generation Costs (annual report series)
- NREL — Annual Technology Baseline (offshore wind)
- Gaertner, E. et al. (2020). IEA Wind TCP Task 37: Definition of the IEA 15-Megawatt Offshore Reference Wind Turbine. NREL/TP-5000-75698
- Global Wind Energy Council — Global Offshore Wind Report
The figures in this guide are typical ranges taken from the listed sources, and your own values will vary with location, prices and equipment. For estimates specific to your site, use the linked calculators.