Four building blocks
Wind needs no fuel, so nearly all the money goes in before the first kilowatt-hour and the payoff is a long, fairly steady income. The page reproduces the heart of a developer’s model in four blocks.
- Yield (P50). Either type in a net capacity factor, or give hub-height wind speed with a Weibull k and the turbine’s specific power. In the second case a generic power curve is integrated across the local speed distribution at the site’s air density, and total losses (wakes, availability, electrical, curtailment) come off the result.
- Cash flow. Income runs at your PPA or market price with yearly indexation. Costs are fixed O&M (land lease and insurance included), variable O&M, degradation of output and, in the last year, decommissioning.
- Financing. A level-annuity loan finances a share of capex and equity covers the rest. You receive the project (unlevered) IRR, equity IRR, NPV at your WACC, and each year’s debt service coverage ratio (DSCR).
- Impact. Land footprint (from rotor diameter and spacing), homes supplied and CO₂ saved.
Equations
Case: a 54 MW onshore farm
Preset: 12 × 4.5 MW turbines (54 MW) with 300 W/m² specific power (138 m rotor), 120 m towers, 7.5 m/s mean wind at hub height and k = 2. Results:
- Energy. Gross capacity factor 43%; losses of 15% bring net to about 36.8%, i.e. roughly 174 GWh yearly, or the consumption of 48,000 EU homes.
- Costs. Capex at 1,400 €/kW totals €75.6 million. Fixed O&M, 42 €/kW/yr, takes €2.3 million a year before variable costs.
- LCOE. About €54/MWh over 30 years at a 6.5% WACC.
- Returns on a €68/MWh sale price (1.5% indexation): project IRR about 12.6%; unlevered NPV €55 million.
- With 70% debt at 5.5% over 15 years: annual debt service €5.3 million, minimum DSCR around 1.75, equity IRR near 20% (pre-tax).
Now try 6.5 m/s. Capacity factor sinks to about 29%, LCOE rises to about the same level as the €68 PPA price, and minimum DSCR slides to a thin 1.28. Wind economics lean hard on the resource.
Interpreting the results
- P50 is the median outcome. Lenders size debt on P90, the output exceeded in 90% of years, which for a single year is usually 8–12% lower. To mimic it, trim the capacity factor or increase the losses.
- LCOE versus price. A price under LCOE destroys value at your discount rate, regardless of payback.
- Project vs equity IRR. Borrowing lifts equity returns when project IRR beats the interest rate, but eats into the DSCR margin.
- Cash-flow chart. Bars stack revenue against O&M and debt service. The right-hand line traces cumulative equity cash and crosses zero in the equity payback year.
Typical parameters
| Parameter | Onshore (Europe/US) | Offshore |
|---|---|---|
| Turbine size | 4–7 MW | 12–15 MW |
| Specific power | 230–330 W/m² | 330–400 W/m² |
| Net capacity factor | 28–42% | 40–52% |
| Capex | 1,100–1,800 per kW | 2,500–4,500 per kW |
| Fixed O&M | 30–55 per kW-yr | 60–110 per kW-yr |
| Total losses | 12–18% | 10–15% |
| Debt share / tenor | 60–80% / 15–18 yrs | 60–75% / 15–20 yrs |
| Design life | 25–30 yrs | 25–30 yrs |
Hints for better projects
- Chase the wind data. An extra 1 m/s of mean speed shifts LCOE 20–30%, so a 12–24 month measurement campaign is cheap insurance.
- Prefer low specific power where wind is moderate. A bigger rotor on the same generator raises capacity factor and revenue per MW and depends less on the strongest, often lowest-priced, hours.
- Trade off layout density. Close spacing gets more MW onto a lease but costs wake loss; 4 × 7 rotor diameters is the usual start.
- Run P90 and price-downside cases before choosing debt terms. On P50, a minimum DSCR below ~1.2 should raise concern.
- Use the LCOE calculator to compare technologies and the wind turbine calculator to refine single-turbine yield.
What is left out
Treat the model as a first screen. Figures are pre-tax: corporate tax, depreciation and tax equity are absent. Connection charges, balancing costs, windy-hour price cannibalisation and curtailment appear only if you fold them into losses, and a single generic power curve with one loss factor stands in for a wake model. Debt is a simple annuity with no sculpting, reserve accounts or construction-period interest. Its job is to rank options and test sensitivities ahead of a bankable yield assessment and financial model.
Method & assumptions
Energy yield. First the rotor: D = √(4P/(π·SP)). For gross output at a given mean speed, integrate a generic power curve (peak Cp 0.46) against a Weibull density and multiply by 8,760 h, i.e. 8,760 h × ∫P(v)·f(v)dv, at the air density of the site's elevation. Net output is gross × (1 − losses). Money: income equals MWh × price (indexed). Costs split into fixed opex (+2%/yr) and variable opex, with decommissioning booked in the final year. LCOE = (capex + Σ opex_t/(1+r)^t) / Σ MWh_t/(1+r)^t. Financing: equity covers capex × (1 − debt share), the loan is a level annuity, and DSCR = cash flow available for debt service ÷ debt service. Land: turbines sit on a grid with spacing sx·D across and sy·D along the prevailing wind.
Frequently asked questions
What is the build cost of a wind farm?
What LCOE does onshore wind reach?
How much ground does a wind farm cover?
Which equity IRR is realistic for wind?
What DSCR will a bank ask for?
How many households can one wind farm supply?
How many turbines does 100 MW take?
Sources & references
- IRENA — Renewable Power Generation Costs in 2023
- NREL Annual Technology Baseline — land-based and offshore wind costs
- Denholm, P., Hand, M., Jackson, M., Ong, S. (2009). Land-Use Requirements of Modern Wind Power Plants in the United States. NREL/TP-6A2-45834
- Short, W., Packey, D., Holt, T. (1995). A Manual for the Economic Evaluation of Energy Efficiency and Renewable Energy Technologies. NREL/TP-462-5173
Embed this calculator
Free for bloggers, installers, schools and NGOs. Copy the snippet below and it stays current by itself.