What does stored energy cost? Levelized cost of storage (LCOS) for batteries

What does a MWh coming out of a battery or other store really cost? Give capex per kWh, O&M, cycle count, depth of discharge, round-trip efficiency, degradation, lifespan, discount rate and charging price; the tool also reports the price spread the store must earn.

Editable share link Branded PDF report Free · no sign-up

Results

Over the project life, one MWh discharged costs 170 $: 104.4 capital, 19 O&M and 46.5 for the energy used in charging (losses included). To cover it, the system needs a spread of about 130 $/MWh over its charging price. Selling at an average 140 $/MWh, it does not cover its costs.
LCOS
170$/MWh
0.17 $ per kWh
Capital share
104.4$/MWh
O&M share
19$/MWh
Charging share
46.5$/MWh
86% round trip
Required spread
130$/MWh
selling minus charging price
Energy capacity
400MWh
Installed cost
100million $
Discharged in year 1
118,800MWh
Capacity at end of life
72%
LCOS breakdown ($/MWh)
LCOS vs cycles per year

Yearly operation

YearCapacityMWh dischargedO&M ($)Charging cost ($)
1100%118,8002,000,0005,525,581
298%116,4242,000,0005,415,070
396%114,0482,000,0005,304,558
494%111,6722,000,0005,194,047
592%109,2962,000,0005,083,535
690%106,9202,000,0004,973,023
788%104,5442,000,0004,862,512
886%102,1682,000,0004,752,000
984%99,7922,000,0004,641,488
1082%97,4162,000,0004,530,977
1180%95,0402,000,0004,420,465
1278%92,6642,000,0004,309,953
1376%90,2882,000,0004,199,442
1474%87,9122,000,0004,088,930
1572%85,5362,000,0003,978,419
  • Capacity fades in a straight line, with no augmentation or cell replacement, although real projects frequently add modules to keep capacity up. Calendar ageing under light cycling is not modelled on its own.
  • LCOS is in real terms and before tax. It leaves out grid connection fees, capacity payments and ancillary service revenue. Battery prices have dropped quickly, so use a recent quote.

Putting one price on storage

A battery or pumped-hydro plant makes no energy of its own. It takes power in, keeps it, and gives most of it back later. Five things decide what each delivered MWh costs: the build bill, how often the plant cycles, its efficiency, how quickly it ages and what the charging power costs. LCOS merges them into one number, so you can rank storage options against each other and against the price gaps they hope to earn.

The method is the one Lazard uses, and the one described by Schmidt et al. in Joule (2019). Your WACC discounts both costs and energy. Capacity shrinks each year, and the energy needed for charging includes the round-trip loss.

Formula

LCOS = [capex + Σ O&M_t ÷ (1+r)^t + Σ (E_out,t ÷ η_RT × P_charge) ÷ (1+r)^t] ÷ Σ E_out,t ÷ (1+r)^t

E_out,t = MW × hours × DoD × SOH_t × cycles per year SOH_t = 1 − capacity loss × (t − 1) (not below 50%)

Required spread = LCOS − charging price

You give O&M as a yearly percentage of capex, which is the habit with batteries. Adding modules to hold capacity, swapping cells and any value left at end of life are all ignored. Projects that do top up their capacity will therefore look slightly worse here than they should.

Walking through the preset

Take a 100 MW battery with 4 hours of storage, so 400 MWh, installed at 250 per kWh. Upkeep costs 2% of capex a year. It does 330 full cycles a year at 90% depth of discharge, returns 86% of the energy it takes in, loses 2% of capacity annually and lasts 15 years. The WACC is 7% and charging power costs 40 per MWh.

  • Build cost: 400 MWh × 250,000 = 100 million.
  • Output in year one is 400 × 0.9 × 330 = 118,800 MWh; by year 15 only 72% of capacity remains.
  • Discounted over the life, the plant sends out about 957,000 MWh. Capital per MWh is therefore 100 million ÷ 957,000 ≈ 104.
  • Add about 19 for O&M and 40 ÷ 0.86 ≈ 46.5 for charging power.
  • The total, LCOS ≈ 170 per MWh, means output must sell for about 130 above the charging price on average. A buyer paying only 140 on average would leave arbitrage short of costs, and that is why many batteries also sell capacity and grid services.

Cycling is the biggest lever on the chart. With 200 cycles a year the LCOS sits well over 200. With 500, and cells that can cope, it falls below 140.

Benchmark values

Round-trip efficiency, installed cost, then LCOS per MWh:

  • Utility LFP, 4 h: 85–90%; 200–350 per kWh; 100–250.
  • Utility LFP, 1–2 h: 86–90%; 300–500 per kWh; 120–300.
  • Home battery of 5–15 kWh: 88–92%; 500–1,000 per kWh; 250–500.
  • Pumped hydro of 8 h and up: 75–80%; 100–250 per kWh; 70–150.
  • Hydrogen, power to power: 30–40%; widely varying cost; LCOS above 300.

Treat these as indicative: they shift with market, year and financing. Battery pack prices fell sharply from 2022 to 2024, so start from a fresh quote.

Reading what comes out

  • LCOS is the average break-even price for each MWh sent out.
  • Required spread is how far above the charging price the plant must sell, on average. Compare it with the peak/off-peak gap in your market. For retail tariffs, the time-of-use savings calculator shows that gap.
  • The breakdown shows which of capital, O&M and charging dominates; charging weighs more when efficiency is low.
  • The yearly table tracks output losses from degradation.

Limits

Revenue stacking is not in the figure: capacity payments, frequency response, avoided demand charges and postponed network upgrades. They can make a project work where arbitrage fails. Ageing also depends on temperature, C-rate and cycling depth, not just years. Tax, grid fees and financing structure are left out. For demand-charge value, try the demand charge calculator, and for generation costs the LCOE calculator.

Method & assumptions

LCOS is the present value of all costs divided by the present value of energy delivered, each year t discounted by (1+r)t. Costs: capex, O&Mt, and charging electricity Eout,t ÷ ηRT × Pcharge. Delivered energy: Eout,t = rated MWh × depth of discharge × state of healtht × cycles. Health falls linearly by the yearly capacity loss to a 50% floor; O&M is a yearly % of capex.

Frequently asked questions

LCOS meaning: what is the levelized cost of storage?
It is a single break-even number for a storage plant. Add up capital, upkeep and the power bought to fill the battery, discount everything to today, and spread it over all the MWh the plant sends out in its life. Where LCOE prices a generator, LCOS prices a store.
How do I calculate LCOS by hand?
Divide the discounted total of capex, O&M and charging bills by the discounted MWh sent out. Each year's output is rated MWh times depth of discharge times remaining capacity times cycles. The charging bill is based on output divided by round-trip efficiency.
Roughly what does lithium-ion storage cost per MWh?
Published 2023–2025 estimates for 4-hour LFP (lithium iron phosphate) plants at utility scale mostly land between 100 and 250 USD per MWh sent out, moving with capex, cycling, financing and the power price paid for charging. Lazard's yearly LCOS study is a popular reference. A home battery cycles less and costs more per kWh, which pushes it to roughly 250–500 per MWh.
Why do cycles per year change the answer so much?
Because the build cost is fixed. Cycle every day and the same capital is spread over twice the output of a plant cycling every second day, so the capital slice of LCOS roughly halves. That gain ends where cell life or degradation limits take over.
Which round-trip efficiency figure is right for my system?
Count from grid in to grid out, with inverter, transformer and auxiliaries included. New LFP systems usually manage 85–90%. Pumped hydro sits at 75–80%, compressed air at 60–70%, and hydrogen at 30–40% once electrolysis, storage and re-electrification are all counted.
Is LCOS the same thing as LCOE?
No. A generator makes energy from fuel, wind or sun, and LCOE prices that. A store buys energy and sells it later, so charging cost and losses enter LCOS. Its income comes from price spreads, capacity payments and grid services, not from making electricity.

Sources & references

  1. Lazard — Levelized Cost of Energy+ (includes LCOS analysis)
  2. Schmidt et al. (2019), Projecting the future levelized cost of electricity storage technologies, Joule 3(1)
  3. NREL — Annual Technology Baseline: utility-scale battery storage
  4. IRENA — Electricity Storage and Renewables: Costs and Markets to 2030