Glossary · Economics

WACC

Weighted average cost of capital: the mix of returns lenders and shareholders require, used as the discount rate when valuing energy projects.

Projects are paid for with a mix of debt and equity. WACC, the weighted average cost of capital, blends the two costs according to that mix.

WACC = (E / V) × Re + (D / V) × Rd × (1 − Tc)

Terms: E equity value, D debt value, V = E + D. Re is the return shareholders demand, Rd is the borrowing rate, and Tc is the corporate tax rate, because interest is generally deductible.

A renewable project with contracted income (PPA or CfD) typically borrows 70–85% of its cost. Example: 5% debt, 10% equity, 80/20 split, 25% tax gives a nominal WACC of 0.2 × 10 + 0.8 × 5 × 0.75 = 5.0%. A merchant plant leans on more equity and pays investors more.

Indicative real after-tax figures for utility-scale solar and onshore wind (IEA, IRENA, 2023–2024) are 3.5–6% for Germany, France, Spain and the US; 7–9% for India and Brazil; and frequently over 10% across sub-Saharan Africa. Dearer capital explains why an identical solar farm can deliver power at two to three times the per-MWh cost in poorer countries, despite better sunshine.

Because it sets the discount rate in LCOE maths, one extra percentage point of WACC adds roughly 7–10% to solar or wind LCOE. The interest-rate climb that began in 2022 helped drive cost overruns and cancelled offshore wind contracts in the US and UK.

Related terms

All terms →
  • Discount rate

    A yearly percentage that converts future costs and income into today's value, capturing both the time value of money and investment risk.

  • LCOE (Levelized Cost of Electricity)

    The flat price per MWh that would repay every lifetime cost of a power plant, once costs and output are both discounted to present value.

  • NPV (Net Present Value)

    Today's value of every future cash flow a project will generate, less what it costs to build; a result above zero means the project creates value.

  • IRR (Internal Rate of Return)

    The discount rate that brings a project's net present value to zero; it expresses the project's effective yearly return.

  • CAPEX

    Short for capital expenditure: the money spent up front to build an energy asset, normally stated per kW (power plants) or per kWh (storage).

  • Contract for Difference (CfD)

    A contract or support scheme that pays a generator the gap between an agreed strike price and a market reference price, and takes money back from it when the market price is higher.