Sizing logic
Brine circulates in a closed plastic loop, either in vertical boreholes or in horizontal collectors under the garden, and carries low-grade heat from the earth to the heat pump, which lifts it to heating temperature. Three linked questions drive the design: what capacity is needed, how much heat is drawn from the soil, and how long a loop keeps the ground from cooling over the years. The calculator follows this sequence:
- Heat demand. Calculated from floor area, insulation (or an annual kWh figure you already have) and hot water, month by month, with temperature bins matched to your climate. Same engine as the air-source heat pump calculator.
- Brine and COP. Unless you supply a value, ground temperature is the annual mean air temperature + 1.5 K. During heating, brine is 4–8 K colder than that, and more so in the coldest months. COP follows from brine and flow temperatures.
- Capacity is set at the design-day heat loss for the location plus a 10% allowance for hot-water recovery.
- Ground extraction. The power drawn from soil is heat output × (1 − 1/SCOP). Next, divide by the specific extraction rate that VDI 4640 gives for your ground type, interpolated to your full-load hours; the quotient is the borehole length or collector area. A cap on yearly energy, 100 kWh per metre per year (60 kWh/m² for horizontal loops), is then applied, and the larger result wins.
- Costs: drilling or trenching, the unit itself, running cost, plus a comparison with air-source heat pumps and gas boilers.
Equations
Case: 180 m² house, Berlin
The default building is a 180 m² Berlin home, average insulation, underfloor heating at 35 °C flow, four people’s hot water. It needs about 18,370 kWh a year and has a design heat loss of 7.0 kW at −9 °C, which leads the tool to choose an 8 kW ground source unit.
With ground at an estimated 11.4 °C, seasonal COP reaches 4.23; an air-source unit in that house would manage about 3.79. Electricity use is about 4,340 kWh, ≈ 1,216 € a year at 0.28 €/kWh. Savings: roughly 141 € yearly versus air source and about 825 € versus a 90% gas boiler (which would cost 2,041 € at 0.10 €/kWh).
The ground supplies about 14,030 kWh yearly. Ground of average conductivity (λ ≈ 2 W/mK) would need about 130 m at roughly 47 W/m on the power criterion alone. The 100 kWh/m yearly cap pushes this to 140 m, e.g. two 70 m boreholes. Drilling at 70 €/m plus 12,000 € for the unit brings installed cost to about 21,800 €. A horizontal collector would instead occupy roughly 290 m². Emissions: about 1.5 t of CO₂ a year at 350 g/kWh grid intensity, versus 3.7 t using gas.
Interpreting the screen
- Borehole length or collector area drives cost; the verdict names whether the energy cap or the power criterion set it.
- Full-load hours above ~2,400 h indicate long seasons (cold climate, heavy hot-water use) and call for lower W/m rates.
- Saving versus air source is what the ground loop’s extra price buys; divide that extra cost by it for rough payback.
- Ground types table gives lengths per geology. A site survey or local drilling records show which applies.
Typical rates by ground (VDI 4640, small systems under 30 kW)
| Geology | W/m, borehole, 1,800 h | W/m, borehole, 2,400 h | W/m², horizontal, 1,800 h |
|---|---|---|---|
| Dry gravel / sand | < 25 | < 20 | 10–15 |
| Moist clay / loam | 35–50 | 30–40 | 25–30 |
| Gravel or sand, saturated with water | 65–80 | 55–65 | 35–40 |
| Limestone (massive) | 55–70 | 45–60 | — |
| Sandstone | 65–80 | 55–65 | — |
| Granite, gneiss | 65–85 | 55–70 | — |
| Basalt | 40–65 | 35–55 | — |
Practical pointers
- Request a thermal response test above ~30 kW or when drilling several holes. Measuring real ground conductivity can trim or extend the field by 20–30%.
- Space holes 6 m apart or more, since closer ones steal each other’s heat.
- Hold flow temperature down. Ground source excels with 35 °C underfloor heating; with 55 °C radiators, its advantage over air source shrinks.
- Think about passive cooling. In summer, circulating brine through the floor cools almost for free and partly restores the ground temperature.
- Lower demand before sizing. The insulation savings calculator helps, and a smaller unit means a shorter, cheaper borehole.
Boundaries
The rates are only a guide: they presume little groundwater movement (which can raise them considerably) and standard single-U or double-U probe construction. Proper simulation (EED, GLHEPro or the MCS MIS 3005 tables) is needed when borehole fields lie close together, operating hours are very long, there are cooling loads, or the system is large. Drilling normally needs a permit, especially past 100 m or inside water-protection zones. Local quotes belong in the advanced settings, as cost varies greatly with country and site access.
Method & assumptions
The model runs each month with temperature bins for space heating and hot water; brine enters the heat pump at Tground − 4 K − 4 K × (monthly load ÷ peak load). Size the unit at design heat loss + 10%. Heat taken from the ground = heat-pump output × (1 − 1/SCOP). The borehole length is that extraction power ÷ the specific extraction rate (W/m) for the ground type, interpolated between the VDI 4640 values for 1,800 h and 2,400 h of full load. Horizontal collector area follows the same logic with W/m².
Frequently asked questions
What borehole depth does a ground-source system need?
What land area does a horizontal ground loop take?
Ground source or air source, which is better?
What does a ground source system cost to install?
What does specific heat extraction rate mean?
Could the loop cool the ground too far?
Sources & references
- VDI 4640 Part 2 — Thermal use of the underground: ground source heat pump systems
- MCS MIS 3005-D — Heat pump design standard (UK Microgeneration Certification Scheme)